Hendersonville Water Department: New Service Connection 2026
Hendersonville, North Carolina · water & sewer connection guide
Need Water at a Hendersonville Property? First Decide: New Account or New Tap
The City of Hendersonville Water & Sewer separates ordinary account setup from a physical water or sewer connection. If the property already has City water and sewer service, use the New Service Application. Do not submit a tap application just because you are a new owner or tenant.
If a property is not currently served, Hendersonville has a separate New Tap, Meter & Service Connection process. Residential projects can require a System Development Fee, Letter of Commitment, tap/meter charges and building-permit coordination before the City installs the service and meter.
Utility / connection questions: (828) 697-3073 · Account & billing: (828) 697-3052
Avoid the wrong application
New Account vs. New Hendersonville Water Connection
The City specifically warns that using the new-tap application for a location that already has Hendersonville water and sewer can delay service being turned back on and transferred into your name.
Moving Into an Existing Property
The property already has City water service, a meter or an established utility connection.
Use:- New Service Application
- Proof of identity
- Lease or ownership documentation
- Customer Service account setup
Property Has No Existing Service
A new tap, meter or sewer connection is required to connect the property to accessible City infrastructure.
Use:- Residential or non-residential tap application
- System Development Fee process
- Letter of Commitment
- Tap / meter installation process
Main Extension May Be Required
If the property does not meet the City’s connection-location criteria, a private utility extension project can be required before service is available.
See Extension RulesCall Water & Sewer at (828) 697-3073 before applying for a new tap if you are unsure whether a meter, stub-out or existing service already exists.
2026 quick reference
Hendersonville Water Department Quick Facts
Property already has service
How to Start a Hendersonville Water & Sewer Account
New Service Application
The City encourages customers to submit the application online or visit Customer Service on the first floor of City Hall at 160 Sixth Avenue East.
Information the City requires
The City’s current application instructions state that all individuals listed on the deed or lease agreement need to be listed as account holders.
The City says rental agreements must be signed by the property management company or property owner. Missing identification or proof of residence can delay or prevent establishment of the account.
Account startup cost
Hendersonville Water Service Deposits in 2026
The 2026–27 City fee schedule uses credit-risk tiers for residential utility deposits.
| Account Type | Risk / Category | Deposit |
|---|---|---|
| Residential water only | Tier 1 – Low risk | $0 |
| Residential water only | Tier 2 – Medium risk | $50 |
| Residential water only | Tier 3 / unable to perform credit check | $75 |
| Residential multiple services | Tier 1 – Low risk | $0 |
| Residential multiple services | Tier 2 – Medium risk | $150 |
| Residential multiple services | Tier 3 / unable to perform credit check | $200 |
| Non-residential water only | All | $75 |
| Non-residential multiple services | All | $225 |
The City’s 2026–27 fee schedule also lists a $10 utility application fee.
Can the property connect?
Hendersonville Water & Sewer Connection Availability Rules
Utility Main Along Property Frontage
A residential or qualifying non-residential connection can be approved when the property fronts an existing public water main or public gravity sewer main.
Within 300 Feet
A connection can also qualify when the property is within 300 feet of an existing public water or gravity sewer main and the connection crosses no more than one other private property.
Private Utility Easement
If the route crosses the one qualifying private property, a private-party utility easement agreement is required.
This changes the project from a basic tap into a utility-extension project with engineering review, construction, inspection and close-out requirements.
Single-family / two-family
Residential New Water Connection Process
Hendersonville installs residential tap connections to accessible water and sewer mains at the customer’s request.
What a standard residential water tap includes
Official residential tap sequence
-
1
Submit the residential tap application
For new construction, Hendersonville says the tap application occurs at the same time as the building-permit application.
-
2
Pay the System Development Fee
The City assesses the water and/or sewer capacity charge based on the project.
-
3
Receive the Letter of Commitment
The City’s Letter of Commitment documents the utility commitment after applicable requirements are satisfied.
-
4
Complete the New Service Application
This establishes the customer billing account.
-
5
Receive the tap / meter bill
The City bills the applicant for applicable tap, meter and service charges.
-
6
Pay the tap and meter charges in full
Applicable charges must be paid before final installation proceeds.
-
7
City installs service and meter
The City completes the qualifying public-side connection and meter installation.
Use this City page for the current tap application and connection instructions.
Capacity charge
2026 Hendersonville Water System Development Fees
Hendersonville began assessing System Development Fees for qualifying new utility demand on January 1, 2025. These charges help recover the cost of system capacity used by new development or increased demand.
2026–27 residential water SDF
| Heated Square Feet | Water SDF |
|---|---|
| Under 1,000 sq. ft. | $1,247.77 |
| 1,000–1,500 sq. ft. | $1,332 |
| 1,501–2,000 sq. ft. | $1,359 |
| 2,001–2,500 sq. ft. | $1,443 |
| 2,501–3,000 sq. ft. | $1,500 |
| 3,001–3,500 sq. ft. | $1,613 |
| 3,501–4,000 sq. ft. | $1,724 |
| Over 4,000 sq. ft. | $1,992 |
The City maintains separate water and sewer System Development Fees. A project requesting both utilities can owe both charges.
Current 2026–27 connection charges
Hendersonville Water Tap, Meter & Connection Fees
| Connection / Meter Service | 2026–27 Fee |
|---|---|
| Water Main Tap & Service — 3/4″ Meter | $1,625 |
| Water Main Tap & Service — 1″ Meter | $1,700 |
| Water Main Tap & Service — over 1″ | Cost |
| 3/4″ Stub-Out + Meter Box + Meter | $975 |
| 1″ Stub-Out + Meter Box + Meter | $1,050 |
| 3/4″ Drop Meter | $350 |
| 1″ Drop Meter | $425 |
| 1.5″ Meter & Setup | $2,045 |
| 2″ Meter & Setup | $2,300 |
| 3″ Meter & Setup | $2,775 |
| 4″ Meter & Setup | $4,474 |
| 6″ Meter & Setup | $7,500 |
| 8″ Meter & Setup | $11,620 |
Other connection-related water charges
A new-development project can also owe the System Development Fee, private plumbing costs, sewer connection costs, building permits, easements, backflow equipment or extension-related engineering and inspection fees.
Real-world budgeting
Example: New 1,800 sq. ft. House With a 3/4″ Water Tap
It illustrates why searchers need to consider both the System Development Fee and physical tap charge. Sewer SDF, sewer tap, private plumber, permitting or extension costs would be additional when applicable.
If sewer is also requested
Residential Hendersonville Sewer Connection Costs
2026–27 single-family sewer System Development Fees
| Heated Square Feet | Sewer SDF |
|---|---|
| Under 1,000 | $2,048 |
| 1,000–1,500 | $2,188 |
| 1,501–2,000 | $2,233 |
| 2,001–2,500 | $2,370 |
| 2,501–3,000 | $2,465 |
| 3,001–3,500 | $2,650 |
| 3,501–4,000 | $2,883 |
| Over 4,000 | $3,273 |
Commercial / multifamily / industrial
Hendersonville Non-Residential New Service Connections
The City’s non-residential process covers multifamily housing, commercial, institutional and industrial uses.
- Water meter is 1.5 inches or larger.
- The project includes a fire-line connection.
- The connection is to a private water or sewer system.
Use the City’s current page for availability, tap, backflow and plan-approval forms.
Meter cannot be installed first
Hendersonville Backflow Requirements
Backflow Required
The City requires an approved backflow-prevention assembly on all non-residential water connections.
Backflow Required
Residential and non-residential irrigation service connections require backflow prevention.
Backflow Comes First
For applicable non-residential service, Hendersonville says the water meter will not be installed until the approved backflow assembly is physically installed on-site.
The City requires applicable backflow-prevention assemblies to be tested annually after installation.
When a tap is not enough
What If the Water Main Does Not Reach the Property?
Hendersonville utility extensions are generally privately funded development projects. The owner’s utility contractor installs the approved water or sewer infrastructure under City inspection. After successful completion and acceptance, the City assumes ownership, operation and maintenance of qualifying infrastructure.
Use the City’s extension page for engineering review, inspections, easements and close-out requirements.
Do not bury before inspection
Water Connection Construction & Inspection Rules
Hendersonville’s Construction & Inspection Division emphasizes this for privately constructed development infrastructure.
Review current City inspection requirements before covering or placing new infrastructure into service.
New construction
Building Permit Coordination for Hendersonville Utility Connections
Permits & Inspections
100 North King Street, Suite 220
Hendersonville, NC 28792
Phone: (828) 697-4830
Hours: Monday–Friday, 8:30 AM–4:00 PM
Why it matters
The City states that development/construction projects must obtain appropriate permits through Henderson County Permits & Inspections. For new residential construction, the City water tap application occurs simultaneously with the building-permit application.
Building permits, tap applications, System Development Fees and utility commitments can affect project sequencing.
Project timing
How Long Does a New Hendersonville Water Connection Take?
It is the City’s stated technician-contact timeframe. Availability, permits, payments, construction complexity and extension requirements can lengthen the full project.
After connection
2026–27 Hendersonville Water Rates
Residential Water
Residential Water
The Hendersonville utility system serves customers both inside and outside City limits, and the current fee schedule uses different base and usage rates for those categories.
Once service is active
Hendersonville Water Account, Bill Pay & Service Fees
Customer Service
(828) 697-3052Monday–Friday, 9:00 AM–5:00 PM.
Service Fee
2.95%Minimum $1.95 under the current Water & Sewer fee schedule.
Late Fee
$10 or 5%Whichever is greater under the current fee schedule.
Use this page to verify current deposits, tap charges, rates, SDFs and miscellaneous utility fees.
Water leak / outage
Hendersonville Water & Sewer Emergency Numbers
The City says only Customer Service can close the billing account. A temporary shutoff for leak repair does not terminate account billing.
Phone, address & hours
Hendersonville Water Department Contact Information
Hendersonville Water & Sewer
305 Williams Street
Hendersonville, NC 28792
Main / Emergency:
(828) 697-3073
Office hours: Monday–Friday, 8:00 AM–4:00 PM
Customer Service Division
City Hall
160 Sixth Avenue East
Hendersonville, NC 28792
Phone:
(828) 697-3052
Hours: Monday–Friday, 9:00 AM–5:00 PM
Henderson County Permits & Inspections
100 North King Street, Suite 220
Hendersonville, NC 28792
Phone:
(828) 697-4830
Hours: Monday–Friday, 8:30 AM–4:00 PM
Account setup location
Map to Hendersonville Customer Service
Avoid delays
Common Hendersonville New Connection Mistakes
The City warns this can delay service activation.
A new tap fee does not include the SDF automatically.
Development, sewer, private plumbing and permits can add costs.
Missing ID, lease or ownership proof can delay account establishment.
The property may require a utility extension instead of a simple tap.
New residential construction coordinates the tap application with permitting.
The meter can be held until required backflow equipment is installed.
Uninspected work can be required to be uncovered, removed or replaced.
60-second action guide
What Should You Do Next?
Understand the terminology
Hendersonville Water Connection Terms
- New Service Application
- The customer account application used when a property already has Hendersonville utility service.
- Tap
- The physical connection between the customer’s service and the public water or sewer main.
- System Development Fee
- A one-time capacity charge assessed to qualifying new development or increases in utility demand.
- Letter of Commitment
- The City’s utility commitment issued during the new connection process after applicable requirements are completed.
- Stub-Out
- An existing service connection prepared to the property area where a meter box and meter can be installed.
- Drop Meter
- Installation of a meter at a location where the required service infrastructure is already prepared.
- Utility Extension
- Construction that extends public water or sewer infrastructure when a normal service connection cannot reach the property.
- Utility Easement
- A legal property interest allowing qualifying utility infrastructure or service to cross private land.
- Backflow Assembly
- A device that protects the public water system from reverse flow or cross-connection contamination.
- Availability Confirmation
- A City review confirming whether utility infrastructure can serve a proposed development.
Primary official resources
Official Hendersonville Water & Sewer Links
10 high-intent answers
Hendersonville Water Department New Connection FAQs
1. How do I start water service in Hendersonville, North Carolina?
If the property already has Hendersonville water or sewer service, complete the City’s New Service Application rather than a new-tap application. Be prepared to provide the legal names of account holders, Social Security Number or Federal Tax ID, service and billing addresses, email, phone number, photo identification and applicable lease or ownership documents. Customer Service can help at (828) 697-3052.
2. Do I need a new tap when moving into an existing Hendersonville house?
Usually not if the house already has a usable Hendersonville water connection. The City specifically warns customers not to use the new-tap application when water and sewer are already provided at the property because doing so can delay account activation. Use the New Service Application instead.
3. How do I apply for a new residential Hendersonville water tap?
Use the City’s Residential Service Connections process. The applicant submits the residential tap application, pays the System Development Fee, receives a Letter of Commitment, opens the customer account, pays applicable tap and meter charges, and then the City installs the qualifying service and meter.
4. How much is a new Hendersonville water tap in 2026?
The City’s 2026–27 fee schedule lists a 3/4-inch water-main tap and service at $1,625 and a 1-inch tap and service at $1,700. Connections over 1 inch are listed at cost. These amounts do not include every possible project expense or the separate System Development Fee.
5. What is the Hendersonville System Development Fee?
A System Development Fee is a one-time capacity charge for qualifying new utility development or increased demand. Residential water SDFs are based on heated square footage. Under the 2026–27 schedule, for example, a 1,501–2,000 square-foot single-family home has a $1,359 water SDF. Separate sewer SDFs apply when sewer service is requested.
6. Can my property get Hendersonville water service if the main is not directly in front of it?
Potentially. The City’s connection criteria allow a qualifying connection when the property fronts an existing public main or when it is within 300 feet of a public water or gravity sewer main and the service crosses only one other private property with an appropriate utility easement. If neither criterion is met, a utility extension is required.
7. How long does a new Hendersonville tap request take?
The City’s Starting Water / Sewer Service page says a technician will contact a new tap, meter or service-connection applicant within approximately 5–10 business days to arrange an appointment and discuss the installation. This is an initial-contact timeframe rather than a guarantee that the entire construction project will be finished within that period.
8. Is backflow prevention required for a Hendersonville water connection?
All non-residential and irrigation connections require approved backflow prevention. For applicable non-residential connections, the City says the water meter will not be installed until the approved backflow assembly has been physically installed. Required backflow assemblies must also be tested annually.
9. What is the Hendersonville Water Department phone number?
The Water & Sewer office main and utility emergency number is (828) 697-3073. Account and billing Customer Service is (828) 697-3052. Utility Administration is located at 305 Williams Street, while Customer Service is located at City Hall, 160 Sixth Avenue East, Hendersonville, NC 28792.
10. What number do I call for a Hendersonville water emergency after hours?
The current Water & Sewer department page lists (828) 697-3073 as its emergency number. City billing and service guidance also lists (828) 891-7779 for after-hours immediate assistance and leak-related service issues. Billing and account questions should be directed to Customer Service at (828) 697-3052 during business hours.